Barrette Piles

Task / Description Slow   Ave   Fast    Units
 Rule of Thumb, overall rate by Mill 0.5  1.1  1.2   hrs/no
 Fabricate reinforcement cages -   4.0  -    hrs/cage
 Concreting barrette panels 40.0  50.0  55.0   m3/hr
 Trimming top of barrette panels -   2.4  -    days/no
 Concrete Testing, Coring Test 4.0  3.5  2.0   days/no
 Concrete Testing, Sonic Logging Test -   0.7  -    days/no

 